Edit/modify project information

You can edit project attribute values if you are signed in as an Administrator or Content manager and the project does not have factors applied.

To edit the project

  1. Find the project. You can browse for a project, or use the search and sort features to help you find a project.
  2. Click Edit on the single project page. 
  3. To change project attribute values:
    • The project attributes are organized by group on the Attributes tab.
    • To ensure all the project attributes are visible and available for editing, select All fields from the Edit view list. To filter (limit) the fields shown in the window, select a different view from the list. (The view list corresponds to the project import templates defined by your administrator in Administration > Project import templates.)
    • Change project attribute values as needed.
  4. Note that you can't change the Project ID when editing an existing project.
    • To enter a comment about an attribute value, hover to the right of the value box and click . For example, if you enter Difficult for a Job site condition attribute, you could enter a comment that explains what makes the job site conditions difficult.
  5. To enter element quantities and comments or notes:
    • Click the Elements tab.

Where do the element quantities (overlines) come from?

The Element quantity column displays either the entered quantity, lookup quantity, or aggregate quantity based on how the expression for the column is configured for your company. Typically, it is configured as follows: 

      1. When an entered quantity is present, it is used for the element quantity.
      2. If an entered quantity is not present, Cortex checks for a lookup quantity and uses it if present.
      3. If a lookup quantity is not present, Cortex checks for an aggregated quantity and uses it if present.
      4. If an aggregated quantity is not present, there will not be an element quantity for the element.

For each element field, the administrator determines how the element quantity is established:

        • Using a lookup for an element: The administrator selects an attribute to use for the element quantity. Cortex Project History looks up the attribute quantity and uses it for the element quantity. For example, the administrator could configure Cortex Project History so that the Project size attribute is the element quantity for Direct costs.
        • Aggregating the quantity for an element: This method adds up all the quantities for the child elements that have a specific unit of measure. The administrator determines the unit of measure to use for aggregating the child element quantities. For example, the aggregate quantity for the Foundations element could be based on CY. In this case, Cortex Project History adds up the quantities for all the child elements (with CY for the unit of measure) in the Foundations group and uses the sum for the Foundations element quantity.
    • From the view list, select the desired element view, such as Uniformat or MasterFormat.
    • Enter quantities, units, comments (comments may be visible to clients), and internal notes (internal notes are for estimates (internal staff) working on the project) for elements as desired.

Element quantities you enter manually override a quantity specified another way.

  1. To manage links for the project, click the Links tab. 

Add a URL

      1. Click Add URL.
      2. In the Add URL window, do the following:
          • Enter a descriptive name for the URL in the Name box.
          • Enter the website address in the URL box.
          • Enter a description or notes about the URL in the Description box.
          • Under Save to folder, select the folder where you want to save the URL.
      3. To add the URL and close the Add URL window, click Save & close. To add the URL and open a new Add URL window, click Save & add.

Add project files

      1. Drop files on the grid, or click Add file, navigate to and select the file to add, and click Open. Note that the file size can't exceed 50 MB.
      2. If you add the file from Windows File Explorer, the Add File window opens:
          • Enter a description for the file, if desired.
          • If Cortex recognizes the file as an image, it makes the image a thumbnail and preselects the Thumbnail check circle in the Add File window.

If you don't want the image to appear in the image slide show on the single project page, clear the Thumbnail check circle.

          • Under Save to folder, select the folder where you want to save the file.
          • To add the file and close the Add File window, click Save & close. To add the file and open Windows File Explorer so you can select another file, click Save & add.

Tip

You can add a new thumbnail image to the project by dragging and dropping the image file on the default image on the single project page.

Edit a link

    1. In the grid, select the link you want to edit.
    2. Click Edit.
    3. Modify the information in the Edit File or Edit URL window, as needed.
    4. Click Save & close or Save & add.

Delete a link

    1. In the grid, select the links you want to delete.
    2. Click Delete.
    3. Click Delete in the Delete Links window to confirm the deletion.

Add a new thumbnail

You can add a new thumbnail image to the project by dragging and dropping the image file on the default image on the single project page

Organize the thumbnails

Use this procedure to change the order that the thumbnail images appear in the image slide show.

    1. Click (Sort thumbnails) in the top right corner of the page.
    2. In the Sort Thumbnails window, use drag and drop to arrange the images in the desired order.
    3. Click Save.

Set the default image for the project

    1. Click (Sort thumbnails) in the top right corner of the page.
    2. In the Sort Thumbnails window, select the desired image and drag it to the top of the list. The first image in the thumbnails list is the default image.
    3. Click Save.
  1. Click Save.


Once Cortex processes the changes, the single project page refreshes automatically so you can see your changes. If any warnings or errors occur while processing the changes, you can see them on the Project imports/updates page for the Edit project event.