Cortex Budget Builder | Edit a Budget

Edit a budget

As you work on a budget, if you don't want to overwrite the current budget with the changes, you can click Save as instead of Save. Saving the budget using a different name is a quick, easy way to create a budget iteration.

How do I?

Open a budget for editing

In the folder pane or budget collection, click the name of the budget you want to edit and click Edit in the budget title bar.

The budget icon ( ) next to the budget name is replaced with an orange pencil icon () to indicate you're in edit mode. 

Change the general budget information

  1. On the budget page, click Edit.
  2. Click the General tab.
  3. Change the general budget information on the General tab as needed. A red asterisk (*) indicates the required fields.
  4. To save your changes and keep the budget open, click Save.

To save your changes and close the budget, click Save & close.

Change attribute values or the attributes tracked for the budget

  1. On the budget page, click Edit.
  2. Click the Attributes tab.
  3. Select different values for attributes as needed. Any values you manually enter will display in bold on the budget attributes tab.
  4. To change the attributes tracked for the budget, click (Settings), and then click Settings in the list. The Selected list shows the attributes currently being tracked for this budget.
    • To add an attribute to the budget, double-click the desired attribute in the Available list to move it to the Selected list. Expand and collapse attribute groups and use the Search box as needed to locate the desired attribute in the Available list.
    • To remove an attribute, double-click it in the Selected list (or select it and click on the attribute) to move it to the Available list.
    • To change the order that the attributes appear on the Attributes tab, use drag-and-drop to rearrange the attributes in the Selected list.
  5. To save your changes and keep the budget open, click Save.

To save your changes and close the budget, click Save & close.

Review or modify elements

Adjust element quantities or costs for the budget

  1. On the budget page, click Edit.
  2. Click the Elements tab.
  3. Change the element quantities and costs as needed. When you make a change in the grid, Cortex recalculates the grid values and briefly displays the affected quantities and costs in orange. 

What happens when I change the quantities or unit costs?

When you change this...

Budget Builder...

Element quantity or Project size

Recalculates the Element total and back-calculates the unit costs (Element unit price and Element total/Project size)

Either of the unit costs

Recalculates the Element total and then back-calculates the other unit cost

Element total

Recalculates the two unit costs and preserves the Element quantity

When you change element information, Budget Builder recalculates the Element total of any parent rows (of the row being edited) based on the aggregation up and any child rows (of the row being edited) are prorated down.

  1. To save your changes and keep the budget open, click Save.

To save your changes and close the budget, click Save & close.

Change (overwrite) a linked element quantity

  1. On the budget page, click Edit.
  2. Click the Elements tab.
  3. Expand the grid to the element level.
  4. Enter the desired quantity for the element in the Element quantity column.

When you enter an element quantity, Cortex changes the quantity for the linked attribute to match. Cortex keeps the linked quantities in sync.

  1. To save your changes and keep the budget open, click Save.

To save your changes and close the budget, click Save & close.

Link an element quantity to a quantity attribute

  1. On the budget page, click Edit.
  2. Click the Elements tab.
  3. Expand the grid to the element level and locate the element.
  4. Right-click the element quantity, click Link to attribute on the shortcut menu, and select the attribute you want to link the element's quantity to. (The shortcut menu lists all the quantity attributes available in the budget.)

Tip

Administrators can also establish element quantity links in Administration > Fields > Item fields > Fields.

Change an element description

  1. On the budget page, click Edit.
  2. Click the Elements tab.
  3. Click the element description (or right-click the element row and click Edit description on the shortcut menu).
  4. Modify the description as needed.

Note that each element must have a unique ID/Description combination.

Click Save to save your changes and close the Edit Description window.

  1. To save your changes and keep the budget open, click Save.

To save your changes and close the budget, click Save & close.

Replace an element in the budget

Add, remove, or re-order the columns on the Elements tab

  1. On the budget page, click Edit.
  2. Click the Elements tab.
  3. Click (Settings) and select Settings in the list.
  4. To add a column, double-click the desired column in the Available list to move it to the Selected list.
  5. To remove a column, double-click it in the Selected list (or select it and click on the column) to move it to the Available list.
  6. To change the column order, use drag-and-drop to rearrange the columns in the Selected list.
  7. To save your changes and keep the budget open, click Save.

To save your changes and close the budget, click Save & close.

Delete an element row on the Elements tab

  1. On the budget page, click Edit.
  2. Click the Elements tab.
  3. Right-click the element row you want to delete, and click Delete row.
  4. Click Delete row in the message box to confirm the deletion. Budget Builder deletes the row along with any child rows.

Note that if you delete all the child rows for a parent row, the parent row retains the total. For example, if you delete all the child rows for A Substructure, A Substructure retains its quantities and totals. You can then edit the parent row as needed.

  1. To save your changes and keep the budget open, click Save.

To save your changes and close the budget, click Save & close.

Show/Hide the Markups grid view

You can show the markups grid view by clicking the blue show/hide icon at the top of the page.

You can hide the markups grid view by clicking the orange show/hide icon at the top of the page

Modify the markups or the markups grid layout

  1. On the budget page, click Edit.
  2. Click the Elements tab.
  3. Modify the markups or Markups grid layout, as needed.

The Subtotal row at the top of the Markups grid is the element direct cost total. The Markups grid is located below the elements grid. Note that the Markups grid is not visible if you are showing statistics or reference data.

    • To change the order of the markups, use the grab dots ( ) to drag the markup row you want to move and drop it in the desired location. You can move a markup within a group or move it to a different group. You can also use drag and drop to move group rows.
    • To modify a budget markup in the Markups grid, click Edit, click the markup you want to modify, and change the desired value. (You can't change calculated values, such as Unit price or % of Budget total.)
    • To add or remove markup columns and total rows for this budget, click in the Markups grid title bar. The Settings page opens.

On the Markup columns tab, drag columns between the Available list and the Selected list to change the columns that display in the grid.

On the Total rows tab, select the check circles of the total rows you want to show in the Markups grid, and clear the check circles of those you do not want to show.

Learn about Markups grid calculations

Column

Description / Calculation

Amount

Subtotal row: This column displays the budget direct cost (i.e., the direct cost total from the elements grid).

Group rows: This column displays the sum total of all the markups in the group.

Markup rows: This column displays the markup amount.

  • For percentage markups, Cortex calculates the markup amount as the Basis * Rate (entered).
  • For lump sum markups, the markup amount is the amount entered.
  • For unit cost markups, Cortex calculates the markup amount as the value of the Quantity field selected as the Basis * Rate (entered).

Markup total row: This column displays the total of all the markups.

Budget total row: This column displays the Budget total.

Budget total - low row: This column displays the Budget total * Budget total - low %.

Budget total - high row: This column displays the Budget total * Budget total - high %.

Unit price

This column displays the Amount / Project size.

Example: $ 99.99 /GSF

Format: Currency over quantity ratio using the Project size unit; 2 decimal places.

This column is calculated and cannot be changed manually.

% of Budget total

This column displays the Amount / Budget total.

Example: 9.999%

Format: Percentage with 3 decimal places

Budget total row: This column is blank.

This column is calculated and cannot be changed manually.

Current total

This column displays the current total only for markup rows.

First markup row: This column displays the Budget direct cost + the first markup.

Subsequent markup rows: Running markup total.

Format: Currency, no decimal places.

This column is calculated and cannot be changed manually.

  1. To save your changes and keep the budget open, click Save.

To save your changes and close the budget, click Save & close. 

Modify the budget total or budget unit price

How does this work?

You can enter the desired budget total or budget unit price to override the total or unit price calculated by Cortex. When you enter a different budget total or unit price, Cortex prorates and distributes your change down through the elements and markups.

  1. On the budget page, click Edit.
  2. Click the Elements tab.
  3. In the Markups grid, locate the Amount or Unit price cell on the Budget total row.
  4. Enter the desired amount or unit price and press ENTER. The Budget Total Change window opens. This window tells you:
    • How much you are increasing or decreasing the budget total by, and
    • The amount that Cortex will distribute to all the elements that are not locked.
  5. Click Submit to apply your change to the budget. 

Manage links for the budget

To manage links for the budget, click the Links tab.

Add a URL

  1. Click Add URL.
  2. In the Add URL window, do the following:
    • Enter a descriptive name for the URL in the Name box.
    • Enter the website address in the URL box.
    • Enter a description or notes about the URL in the Description box.
    • Under Save to folder, select the folder where you want to save the URL.
  3. To add the URL and close the Add URL window, click Save & close. To add the URL and open a new Add URL window, click Save & add.

Add files

  1. Drop files on the grid, or click Add file, navigate to and select the file to add, and click Open. Note that the file size can't exceed 50 MB.
  2. If you add the file from Windows File Explorer, the Add File window opens:
    • Enter a description for the file, if desired.
    • If Cortex recognizes the file as an image, it makes the image a thumbnail and preselects the Thumbnail check circle in the Add File window.

If you don't want the image to appear in the image slide show on the single budget page, clear the Thumbnail check circle.

    • Under Save to folder, select the folder where you want to save the file.
  1. To add the file and close the Add File window, click Save & close. To add the file and open Windows File Explorer so you can select another file, click Save & add.

Tip

You can add a new thumbnail image to the budget by dragging and dropping the image file on the default image on the single budget page.

Edit a link

  1. In the grid, select the link you want to edit.
  2. Click Edit.
  3. Modify the information in the Edit File or Edit URL window, as needed.
  4. Click Save & close or Save & add.

Delete a link

  1. In the grid, select the links you want to delete.
  2. Click Delete.
  3. Click Delete in the Delete Links window to confirm the deletion.

Lock an element row

  1. In the grid, select the row you want to lock.
  2. Right click on the row and select Lock row. 
  3. All child elements nested under a parent element will also be locked. A lock icon () appears to the left of all locked element rows.  
  4. Click Save & close.

Unlock an element row

  1. In the grid, select the row you want to unlock.
  2. Right click on the row and select Unlock row. 

All child elements nested under a parent element will also be unlocked. The lock icon () in the row will disappear confirming the row is unlocked.

  1. Click Save & close

Organize the thumbnails

Use this procedure to change the order that the thumbnail images appear in the image slide show.

  1. Click (Sort thumbnails) in the top right corner of the page.
  2. In the Sort Thumbnails window, use drag and drop to arrange the images in the desired order.
  3. Click Save.

Set the default image for the budget

  1. Click (Sort thumbnails) in the top right corner of the page.
  2. In the Sort Thumbnails window, select the desired image and drag it to the top of the list. The first image in the thumbnail list is the default image.
  3. Click Save. 

Add reference projects to the budget

  1. On the budget page, click Edit.
  2. Click (Add projects).

If budget values are linked to statistics, the Add/Remove Reference Projects window notifies you that changing the reference projects for the budget will cause those statistics to recalculate and update the budget values accordingly.

To continue, click OK. To review the statistic links, click Cancel.

  1. The Search Projects window opens next. Enter keyword(s) (e.g., office) for searching your projects and click Search. The project search results open.
  2. Filter the project search results, as needed.
  3. Select the projects you want to add to the budget and click Add projects.

The new projects appear as reference projects on the Attributes and Elements tabs. Cortex recalculates all the statistics to reflect the projects you added and updates the linked budget amounts.

  1. To save your changes and keep the budget open, click Save.

To save your changes and close the budget, click Save & close.

Remove reference projects from the budget

  1. On the budget page, click the Attributes or Elements tab. Make sure you are showing reference data.
  2. Click Edit.
  3. To select the reference projects you want to remove, check the blue circle next to the project name.
  4. Then click (Remove projects).

If budget values are linked to statistics, the Add/Remove Reference Projects window notifies you that changing the reference projects for the budget will cause those statistics to recalculate and update the budget values accordingly.

To continue, click OK. To review the statistic links, click Cancel.

  1. Cortex removes the selected projects from the budget, recalculates all the statistics to reflect the projects you removed, and updates the linked budget amounts.
  2. To save your changes and keep the budget open, click Save.

To save your changes and close the budget, click Save & close. 

Apply factors to a budget

  1. On the budget page, click Edit.
  2. Click to open the Budget Factors window.
  3. Under Rate tables, select the desired factors to apply to the budget. For example, select a different state, city, and year from the Location & Date lists.

The switch at the bottom of the Budget Factors window controls whether multipliers or percentages display.

How do multipliers work?

Multipliers are base 100. For example, if a factor of 100 is applied, it has no impact—100 is a 0% change. A multiplier of 80 correlates to -20%.

  1. To apply one or more adjustment factors to the budget, enter values (as a multiplier or a percentage based on the setting at the bottom of the Budget Factors window) in the boxes under Adjustments.

To see the note for an adjustment, hover over next to the adjustment name.

To clear an adjustment, click next to the adjustment box.

  1. Click Apply to apply the factors.

The factors you applied display in a yellow banner at the top of the single budget page and the factored values display on the budget page. Amounts directly impacted by factoring or recalculated because of the applied factors appear in bold.

Remove factors from a budget

  1. Click on the actions bar to open the Budget Factors window.
  2. Click Clear all factors at the bottom of the window.
  3. Click Apply.

Lock a budget

Locking the budget will prevent other users from making changes to the budget until you choose to unlock it.

  1. Highlight the budget you want to lock and right click to display the drop down menu.
  2. Click Lock budget.

Unlock a budget

Unlocking the budget will allow other users to make changes to the budget.

  1. Highlight the budget you want to unlock and right click to display the drop down menu.
  2. Click Unlock budget.