What are factor targets?

The administrator sets up factor targets to specify what to adjust using rate tables. For example, to adjust direct labor only (hours and cost), the administrator selects the General labor amount and General labor hours fields as factor targets. The factor targets are the same for all rate tables.

How do I?

Open the Administration module

Click and select Administration from the menu. The Administration module opens in a new browser tab.

Specify what you want to adjust using rate tables

You can use rate tables to adjust non-calculated numbers, quantities, or costs for project fields or item fields.

  1. In the Administration module, click Factors > Factor targets in the options list.
  2. Click the Project targets tab.

Fields based on expressions are not available on the Project targets tab. Any project-level fields based on expressions that aggregate from the details are automatically affected. However, if you want to adjust an input field, like Contract amount, you can select it on the Project targets tab.

Review the fields in the Available list. Use drag and drop to move any fields you want to adjust to the Selected list. Only the fields you want adjusted should display in the Selected list.

  1. Click the Element targets tab.

Cortex automatically selects all the element cost fields because cost type element fields are used for aggregations at the project level and represent the cost of the project. When you create an element cost field, Cortex adds it to the Selected list.

Review the other element fields in the Available list. (Fields based on expressions are not available on Element targets tab.) Use drag and drop to move any fields you want to adjust to the Selected list. Again, only the fields you want adjusted should display in the Selected list.

  1. Click the Item targets tab.

Cortex automatically selects all the item cost fields because cost type item fields are used for aggregations at the element and project levels and represent the cost of the project. When you create an item cost field, Cortex adds it to the Selected list.

Review the other item fields in the Available list. (Fields based on expressions are not available on Item targets tab.) Use drag and drop to move any fields you want to adjust to the Selected list. Again, only the fields you want adjusted should display in the Selected list.

  1. Click Save.